• Tylerdurdon@lemmy.world
    link
    fedilink
    English
    arrow-up
    0
    ·
    4 months ago

    I would have lifted up, then pulled the train out, then lowered and pulled manageable quantities.

    • 0x4E4F@sh.itjust.worksOP
      link
      fedilink
      English
      arrow-up
      0
      ·
      edit-2
      4 months ago

      Actually, everything should be done by crane, but I guess management told them to use the forklifts cuz getting and assembling one on site costs a lot.

        • 0x4E4F@sh.itjust.worksOP
          link
          fedilink
          English
          arrow-up
          0
          ·
          4 months ago

          No, but tell that to Bob from management, who is not an engineer.

          I’ve been in situations like that. You just don’t do it. Also, explain why in written form and have that stamped and submitted.